Hi,

I have some updates on production for everybody. To recap what I explained
we have two Milestones to pass before flipping the Mass production switch.
DVT and PVT.

DVT. The phones from Design Verification Test have been characterized and
have been passed back to engineering. So, we are proceeding with a series of
PVT builds to test the production worthiness of the design.

As those PVT runs get going, I'll update everyone on the results.