Om2009 release plan

Angus Ainslie nytowl at openmoko.org
Wed Apr 8 15:34:23 CEST 2009


On Tue, 2009-04-07 at 22:53 +0200, Ed Kapitein wrote:

> Hi,
> 
> With the remainder of march being behind us, can you give an update on
> the release plan?
> 
> Kind regards,
> Ed
> 

Hi Ed,

We are going to put a testing image together for the end of this week.
Because of OM reduced staffing levels some other dates mentioned in the
Release Plan will probably slide a bit.

Most of the features mentioned in the release plan have been
implemented. A few still need some work and hopefully we can get those
finished in short order.

Angus