Rod Whitby wrote:
> Michael Shiloh wrote:
>> GTA02:
>> ------
>>
>> We are entering the last phases of finalizing the design. From this
>> point forward there are three key milestones in the life of a hardware
>> platform: Prototype runs; a pilot run; and mass production. We have made
>> three prototype runs to test various subsystems. Our best case analysis
>> of the schedule indicates that GTA02 will be ready for shipment to end
>> users in early to mid December.
> 
> Is that mid-December for:
> 
> a) the pilot-run P0 developer end users (just like the P0 50-units free
> phase of GTA01), or
> 
> b) the mass production P1 developer end users (just like the P1 GTA01
> phones currently being sold), or
> 
> c) the mass production P2 general market software-ready end users?
> 
> We understand that schedules are hard to estimate and will vary wildly
> based on things outside the control of those estimating the timeframes,
> but we can still be very precise about exactly *what* it is that we are
> hearing time-scale estimates for ;-)

I would guess b), but let me confirm.

Michael
-------------- next part --------------
A non-text attachment was scrubbed...
Name: michael.vcf
Type: text/x-vcard
Size: 237 bytes
Desc: not available
Url : http://lists.openmoko.org/pipermail/community/attachments/20070928/983f22af/attachment.vcf 


More information about the community mailing list